White Cart Water Flood Prevention Scheme

White Cart Water FPS Home > Phase 3 > Programme

Programme

Glasgow City Council are delivering this project to a tight timescale to ensure, now that funding is available, that flood protection is delivered to the final residents and businesses that could be affected as soon as possible. Key stages through the project are noted below:

Consultation - Initial contact public and stakeholder June-August 2017

Tender Issue to Contractors - late Summer/early Autumn 2017

Contract Awarded to RJ McLeod - February 2018

Start on Site - March 2018

WS2 Snuff Mill - April 2018 to August 2018

WS3 Old Castle Road - August 2018 to May 2019

WS7 Margaretta Buildings - May 2018 to October 2018

WS23 Auldhouse Park - June 2018 to August 2018

WS33 Auldburn Road - April 2018 to October 2018

WS35A TA Centre - May 2018 to September 2018

WS35B Greenbank Park - May 2018 to September 2018

WS36 Hippingstones - April 2018 to October 2018

WS37 Damshot Crescent - May 2018 to September 2018

WS99 Pollock Park - June 2018 to October 2018

Overall Completion - May 2019