
White Cart Water FPS Home > Contract 2 > programme
Contract 2 - scope
Contract 2 comprises the construction of approximately 4.5km of flood defence walls and embankments along sections of the White Cart Water and Auldhouse Burn together with the raising of two footbridges and the construction of six underground pumping stations. The map below shows those areas where flood defences will be constructed as part of this contract.
The following table summarises the construction works to be undertaken at each of the Work Sections identified in the plan above:
| Work Section | Summary of work to be undertaken |
| 4 | Construction of approx 82 linear metres of new reinforced concrete retaining wall. |
| 5 | Construction of approx 215 linear metres of new reinforced concrete retaining wall. |
| 6 | Construction of approx 55 linear metres of new sheet piled flood defence wall. |
| 8 | Construction of approx 110 linear metres of new sheet piled flood defence wall. |
| 9 | Construction of approximately 300m of reinforced concrete retaining wall in front of existing concrete retaining wall. |
| Construction of underground pumping station. | |
| 10 | Construction of approximately 110 linear metres of reinforced concrete flood defence wall. |
| 11 | Construction of approximately 260 linear metres of reinforced concrete flood defence wall. |
| 12 | Raising of existing 22m clear span steel Warren truss pedestrian bridge by 800mm at both ends. |
| 13 | Raising of existing 23m clear span steel and concrete Vierendeel truss pedestrian bridge by 800mm at one end only. |
| 14 | Construction of approximately 65 linear metres of reinforced concrete flood defence wall and approximately 200 linear metres of new sheet piled flood defence wall. |
| Construction of 2 no. underground pumping stations. | |
| 15 | Construction of approximately 330 linear metres of new sheet piled flood defence. |
| 16 | Construction of approx 216 linear metres of flood defence wall. |
| Construction of underground pumping station. | |
| 17 | Construction of approximately 480 linear metres of new sheet piled flood defence. |
| Construction of underground pumping station. | |
| 18 | Construction of approximately 240 linear metres of reinforced concrete flood defence wall. |
| 19 | Construction of approximately 85 linear metres of new reinforced concrete wall and 150 linear metres of new sheet piled flood defence. |
| 20 | Construction of approximately 140 linear metres of new sheet piled flood defence. |
| 24 | Construction of approximately 310 linear metres of new sheet piled flood defence. |
| 25 | Construction of approximately 152 linear metres of new reinforced concrete retaining wall. |
| 27 | Construction of approximately 200 linear metres new reinforced concrete retaining wall and 83 linear metres of new sheet piled flood defence wall on right river bank. |
| Construction of approximately 74 linear metres of new sheet piled flood defence wall on left river bank. | |
| 28 | Construction of approximately 147 linear metres new sheet piled flood defence wall on right river bank and 145 linear metres on left river bank. |
| Construction of underground pumping station. | |
| 29 | Construction of approximately 144 linear metres new sheet piled flood defence wall. |
| 39 | Existing manhole covers to be removed and replaced with watertight covers. |
| 41 | Existing manhole covers to be removed and replaced with watertight covers. |
In some areas e.g. Spean Street, prior to the flood defence works commencing it is necessary to divert existing pipes and cables. This work will be carried out by the utility companies (BT, Scottish Power, Thus etc) over the next six months.
In most areas the first activity to be carried out is securing the site with new fencing which will be followed by tree felling and site clearance.