White Cart Water FPS Home > Contract 2 > programme
Contract 2 - programme
Construction started in January 2009 and is due for completion in October 2011.
| Work Section | Anticipated Start Date | Anticipated Finish Date |
| 4 | 26-02-09 | 24-07-09 |
| 5 | 07-10-09 | 17-02-10 |
| 7 | 17-02-09 | 23-07-09 |
| 8 | 10-06-09 | 14-09-09 |
| 9 | 27-07-09 | 29-07-10 |
| 10 | 17-08-09 | 13-11-09 |
| 11 | 02-12-09 | 02-06-10 |
| 12 | 03-12-09 | 28-01-10 |
| 13 | 15-01-10 | 20-04-10 |
| 14 | 03-03-10 | 30-11-10 |
| 15 | 01-12-10 | 13-07-11 |
| 16 | 15-03-10 | 03-09-10 |
| 17 | 14-09-09 | 13-05-10 |
| 18 | 23-03-10 | 03-09-10 |
| 19 | 28-09-09 | 26-04-10 |
| 20 | 07-09-09 | 15-02-10 |
| 24 | 27-04-09 | 26-10-09 |
| 25 | 09-02-09 | 06-07-09 |
| 27 | 30-03-09 | 18-02-10 |
| 28 | 07-09-09 | 14-05-10 |
| 29 | 30-11-09 | 24-03-10 |
| 39 | 07-05-09 | 05-08-09 |
| 41 | 07-04-10 | 20-04-10 |